A plant that cannot stop forces you to migrate by business process, not by system. Coexistence stopped being a problem and became the strategy.
Salmon producer with continuous processing and plants in southern Chile. A 24/7 operation: every hour without interfaces means product stalled on the line and shipments that do not leave.
The installed base ran on SAP PO 7.5 with multiple productive interfaces: EDI with international retail chains, electronic invoicing, warehouse management integration and master data replication into S/4HANA. Standard maintenance for PI/PO ends on 31 December 2027 and the paid extension raises support costs significantly. The project was not optional, it was a date.
The decision that shaped the project was not technical: it was accepting that PO and Integration Suite would coexist for several weeks, and designing the cutover by business process rather than by system.
The usual alternative — migrate everything and cut over in one window — was impossible without downtime. Instead we grouped by process: first the least critical interfaces with no external counterparty (internal master data), then logistics, and last EDI and electronic invoicing, which involve third parties and hurt most when they go wrong.
During coexistence, PO remained the entry point and routed traffic to Integration Suite per migrated process. That allowed a whole group to be rolled back within minutes without touching the others. The rollback was never needed in production, but its existence is what made it safe to move fast.
A real interface inventory measured against observed traffic, not against documentation: some of the declared interfaces had not processed a message in over a year and were retired rather than migrated. The rest were rebuilt as iFlows with explicit error handling — retries with backoff and a shared exception subprocess — instead of replicating the PO's implicit behaviour. Each group ran in parallel on both platforms for several days, comparing outputs before traffic was cut over.
The migrated iFlows went live on Integration Suite within the committed timeline, with no production outage and no incidents reported by EDI counterparties during cutover. Several obsolete interfaces that were still being maintained were retired. The client was left with homogeneous error handling and message traceability that did not exist before.
In an environment with no downtime windows, coexistence is not a phase to be shortened: it is the tool that makes the project possible. What needs careful design is not the cutover, it is the ability to go back.
This case study is anonymized because of contractual confidentiality, not personal data protection rules: it concerns an organization, not an individual. Under an NDA, we can provide references you can contact.